You are here

Change the status of an issue to 'Work done' using Aconex Field

Once you've completed your work, close the issue.
  1. Log in to Aconex Field using your regular Aconex login name and password.
  2. Click Issues and select the area of the project where the issue is located.
  3. Find the issue you want to mark as done.
Editing an issue's status
  1. Roll over the issue's status on the right-hand side, and a pencil icon will appear.

  2. Click the status label, and select Work Done from the dropdown menu that appears. The issue status will update.

Updating the status to 'work done'

The inspector on your project will see that you have completed the work. They will inspect your work and, if they're satisfied, they'll close the issue.

Feedback